N class 31874 Boiler Overhaul Update – September 2015

Work is progressing well on 31874’s boiler at Adam Dalgleish Engineering Ltd. in Stockton. The boiler is the biggest single expenditure of the overhaul due to the amount of work required, most of which is specialist and can only be carried out by a handful of people in the UK.

boiler lift
31874’s boiler as removed

Work to date has mainly consisted of stripping the boiler and cutting out the sections of firebox platework that needed replacing, and forming the new sections of copper and steel platework ready for them to be fitted and welded in to place. The first major step of reassembly to be completed was the welding in of the new copper inner firebox backhead a few weeks ago.

11906960_597893003685611_139792987_o
New inner firebox backhead welded in to place

More recent progress with the boiler has included the inner throatplate section being welded in, both inner side plates prepped and fitted ready for welding in next week, the smokebox angle ring being riveted and caulked, and the new section for the foundation ring machined to size before fitting.

11935622_597892957018949_1453183066_o
Front tubeplate removed
11939108_597892997018945_933805293_o
Side view of firebox showing some of the hundreds of stays being renewed
11901521_597893007018944_1462740058_o
Side view of the firebox showing the lower inner and outer half sides removed
11901004_597892983685613_30366699_o
View from the other side showing the same plates being renewed on both sides of the firebox